Page 1 of 1
Extreme Marshmallow Cannon
User-Contributed Project
This project guide is not managed by MAKE staff.
These are complete directions on how to put together the Extreme Marshmallow Cannon. Some steps will require 2 people.
- Author: Joe Hudy
- Time required: 5-8 Hours
- Difficulty: Moderate
This project will take about 8 hours. It doesn't need to be done all in one sitting. Enjoy and take your time.
Tools
Relevant parts
- 8oz PVC Cement Red Hot Low Voc
- Pressure Gauge 0-100 PSI
- Electronic Sprinkler Valve
- 9V Battery (2)
- Switch

- Wire

- Bike Tire Valve
- Marshmallows
- Altoids Box
- PVC Tape
- PB110 1/2" x 1/4" Brass Pipe Bushing
- PB101 1/4" Brass Pipe Tee
- PB113 1/4" Close Brass Pipe Nipple
- PVC 1 1/2" EL 90D EL (4)
- PVC 3/4" EL 90D EL
- PVC 1" x 1" x 3/4" Tee
- PVC 3/4" x 3/4" Tee (2)
Relevant parts (continued)
- PVC 1-1/2" x 1 1/2 x 1" Tee (2)
- PVC 1 1/2" x 1 1/2" x 1 1/2" Tee
- PVC 1-1/2" Cross
- PVC 3/4" Running Trap (2)
- PVC 1" Male Adapter (2)
- PVC 1" x 3/4" Bushing (2)
- PVC 1-1/2" x 1" Bushing
- PVC 3/4" x 1/2" Bushing
- PVC Marshmallow Barrell
- PVC 1 1/2" x 12" (2)
- PVC 1 1/2" x 10"
- PVC 1 1/2" x 6 1/2"
- PVC 1 1/2" x 2 1/2" (4)
- PVC 1 1/2" x 3 7/8" (1)
- PVC 3/4" x 1 1/2" (3)
- PVC 1" x 2 1/2" (1)
- PVC 1" x 2" (1)
- View:
- Paginated
- Full width

Edit
Step 3
¶
Lay out pieces to make sure you have everything.
Dry-fitting the entire project is a great idea. Some pieces may need to be sawed down to fit correctly. Lining up the handle can be tricky.
Draw guide marks. These will help you know when you've pushed the pipe in far enough, and keep it level.
Picture 2 shows an example of guide marks.

Edit
Step 4
¶
We will be starting with the bottom and working upwards.
Remember: PVC glue dries VERY fast.
You will spread PVC glue around the short pieces and inside the shaped pieces.
Push and twist together. Make VERY sure that they are all level. If they are not level the rest of the pieces will not fit.
Quickly after/while inserting the pieces we laid it flat on the table and pushed it flat. This makes sure the whole base is level.

Edit
Step 15
¶
Before and after paint
Put a 12" piece of PVC into the top. This is where the marshmallows will be loaded and fired.
You will need to solder wires from the sprinkler valve, switches and extra wire to battery pack. Hide battery in Altoids can.
One switch is your safety, the other is the firing switch.
Load marshmallow. Pump with bike pump to 30 PSI. Flip your safety off and fire. The marshmallows will go far, so make sure you have a safe area to shoot them.
WARNING: Only pump the air cannon to 30PSI. Any more could result in damage to cannon or yourself.
This guide has been completed 3 times.
Page 1 of 1
Comments 
Comments are onturn off
krstnmullet, · Reply
yes i can :) . all you have to do is take 2 9volt battery clip's and positive to negitive and then you van just connect the led's of the valve witch ever way you want.
Great thanks!
krstnmullet, · Reply
How long did you make the 2 side pieces? they look way longer than 12"
krstnmullet, · Reply
@krstnmullet they are 12 inches.

Can you expand on how you wire the switch to the battery and sprinkler valve?
thankyou